Project Details
- Location
- Dumbo, Brooklyn
- Building Type
- Condo
- Scope
- Full gut bathroom renovation
- Timeline
- 4 weeks
- Investment Range
- $30,000–$35,000
- Key Challenge
- Board/alteration agreement approval, tight footprint, full electrical rewire

Bathroom Renovation
A full gut bathroom renovation in a Dumbo, Brooklyn condo, completed in four weeks. The project included condo board and alteration agreement approval, a compact layout, and a rewire of the vanity lighting circuit. Finishes include gray stone-look wall tile, a glass tub and shower enclosure, a dark-wood vanity, and an LED mirror cabinet.
Case Study
Project scope, the challenges involved, and the completed result.
Overview
Alpha Contracting completed a full gut renovation of a bathroom in a Dumbo, Brooklyn condo. The rest of the home had recently been updated, and the original bathroom was small and dated by comparison. The owners set a four-week timeline and a budget of $30,000 to $35,000, and the work had to proceed under the building's alteration agreement.
The Challenge
The building required board approval of an alteration agreement before any work could begin. That is standard in a well-managed condo, but on a four-week schedule it had to be completed early. The bathroom's compact footprint also called for careful planning of the vanity, storage, and tub enclosure.
After demolition, we found that the existing wiring at the vanity could not safely support the new LED mirror cabinet and light fixtures. What had been planned as a fixture replacement became a rewire of the lighting circuit back to its source.
Our Approach
We submitted the alteration agreement documentation at the start of the project, so board approval did not delay construction. Once the wiring issue was found, we opened a larger section of wall to assess it fully. Our licensed electrician spent a full day tracing the fault to its source and then rewired the lighting circuit.
Correcting the wiring at the source added a day to the schedule. It also removed the risk of a lighting failure or a callback after the project was closed out.
The Result
The completed bathroom is bright and makes good use of the available space. Gray stone-look tile surrounds the tub and shower, with a glass sliding enclosure. The room also includes a dark-wood vanity with a white top, an LED anti-fog mirror cabinet, light marble-look floor tile, and chrome fixtures. The project was completed in four weeks and within budget.
Project Details
Related Links
Scope
Project Gallery
A closer look at the details, finish work, and progression of the completed space.







Project FAQs
Common questions about projects like this one, answered from this renovation.
Next Step
If this project is close to the level of detail or finish you are after, send over your scope and we can talk through the next step.